Thursday, 26 February 2009

Spring is on the way !

Stage 3B





As you can see from the photos, good progress is being made with the additional Stage 3B trackwork. The top photo shows the new point giving access to Stage 3B being fitted in on Wednesday this week, and the other two show the revised track and points allowing access back into the station area..



All photos: Brian M

We are also progressing the treatment of the workshop & loco shed elevations in our green & cream colours, and work is continuing with Lucille's improvements which include new sight glasses, a hand pump to help out when the injectors won't !, and she is due for a repaint .....so still lots to do before our first Open Day in May, and we can just feel the Spring like weather forcing nature to do what she has to do with the new growth of grass and general tree & shrub vegetation, all of which needs to be restrained, often !
Roll on Summer !